A48Facilitate emission reduction activities in the industrial and business sector

Progress

  • Not started
  • Planning
  • Implementation
  • Continuous
On time

Council’s Zero Emissions Business Lead continues to make made significant progress engaging with large manufacturing businesses with large energy loads (160 MWh/year plus). In the last 6 months total of 3,100 MWh electricity savings and 5,230 GJ of natural gas savings has been identified. This equates to over 3,800 tCO2e savings / year and cost savings of $780,700 for local businesses. In addition, up to 3,455kW of solar PV of has been proposed, which equates to savings of over 3,400 tC02e/ year (proposed).

  • Priority (high, medium, low)

    High

Summary and contacts

Timeline

Continuous

Department

Contact persons

  • Anthony Thyriar
    Zero Emissions Business Project Lead
    Kingston City Council
Information updated 01.08.2024